(Posted 2/19/13) Major electrical work started Saturday to install new main electrical distribution panels for each campus building and new switchgear cabinets (shown above) in the main switchgear room. The work is proceeding in phases starting with the West Building (completed on Saturday, 2/16/13) and moving to the North Building, and then the East Building. Each phase lasts approximately 12 hours and is further compartmentalized to minimize power disruption to individual spaces. This work is a major component of the recovery work related to the superstorm.